S-34.1, r. 1 - Regulation respecting petroleum exploration, production and storage in a body of water

Full text
159. The authorization holder must draw up a daily report of the work and keep it on the activity site.
The daily report must contain all the elements applicable to the declared day including, in particular,
(1)  the drilling authorization number;
(2)  the name of the drilling installation;
(3)  the number of persons on board the drilling installation;
(4)  a description, in chronological order, of the work carried out and the time required for carrying out each step of the work;
(5)  the name of the enterprises that carried out the work;
(6)  the operating condition of the blowout prevention system;
(7)  the measured depth reached during the day;
(8)  the composition of the drilling fluid and the spacer fluid and the volumes used;
(9)  a loss of circulation;
(10)  the components used to assemble the drill strings;
(11)  the specifications of the casing and its setting depth;
(12)  the weight applied to the bit and its penetration rate;
(13)  the measurements of the deviation of the well path in dip, azimuth and depth;
(14)  traces of petroleum or water detected;
(15)  the type of pump used and its capacity;
(16)  the type of cement used, its density, its additives and their proportions, its setting time and the volume used;
(17)  the well logs carried out;
(18)  the observations and data related to the evaluation or characterization of the geological formation;
(19)  the fluid samples collected;
(20)  the results of the pressure and leak tests;
(21)  the volume and composition of the gas used, released, incinerated or burned at the flare;
(22)  the composition, concentration and detailed assessment of all the products identified in the technical program that are stored or used on the activity site;
(23)  the operational problems encountered and the corrective measures taken or planned;
(24)  the indication of any temporary drilling work interruption and the procedure followed to secure the well;
(25)  the indication of any event that disrupted the progress of the work;
(26)  the abnormal meteorological conditions that caused an operation delay, in particular, due to
(a)  visibility;
(b)  temperature variation;
(c)  wind speed or direction;
(d)  the height, period and direction of the waves and swells;
(e)  the size, distance and direction of ice;
(f)  icing; and
(g)  rolling, pitch and vertical motion of the vessel or platform; and
(27)  any other information or document deemed necessary by the Minister.
O.C. 1251-2018, s. 159.
In force: 2018-09-20
159. The authorization holder must draw up a daily report of the work and keep it on the activity site.
The daily report must contain all the elements applicable to the declared day including, in particular,
(1)  the drilling authorization number;
(2)  the name of the drilling installation;
(3)  the number of persons on board the drilling installation;
(4)  a description, in chronological order, of the work carried out and the time required for carrying out each step of the work;
(5)  the name of the enterprises that carried out the work;
(6)  the operating condition of the blowout prevention system;
(7)  the measured depth reached during the day;
(8)  the composition of the drilling fluid and the spacer fluid and the volumes used;
(9)  a loss of circulation;
(10)  the components used to assemble the drill strings;
(11)  the specifications of the casing and its setting depth;
(12)  the weight applied to the bit and its penetration rate;
(13)  the measurements of the deviation of the well path in dip, azimuth and depth;
(14)  traces of petroleum or water detected;
(15)  the type of pump used and its capacity;
(16)  the type of cement used, its density, its additives and their proportions, its setting time and the volume used;
(17)  the well logs carried out;
(18)  the observations and data related to the evaluation or characterization of the geological formation;
(19)  the fluid samples collected;
(20)  the results of the pressure and leak tests;
(21)  the volume and composition of the gas used, released, incinerated or burned at the flare;
(22)  the composition, concentration and detailed assessment of all the products identified in the technical program that are stored or used on the activity site;
(23)  the operational problems encountered and the corrective measures taken or planned;
(24)  the indication of any temporary drilling work interruption and the procedure followed to secure the well;
(25)  the indication of any event that disrupted the progress of the work;
(26)  the abnormal meteorological conditions that caused an operation delay, in particular, due to
(a)  visibility;
(b)  temperature variation;
(c)  wind speed or direction;
(d)  the height, period and direction of the waves and swells;
(e)  the size, distance and direction of ice;
(f)  icing; and
(g)  rolling, pitch and vertical motion of the vessel or platform; and
(27)  any other information or document deemed necessary by the Minister.
O.C. 1251-2018, s. 159.